SECTION 202 AND SECTION 811- DEVELOPMENT TEAM REFERENCE GUIDE
For Project Development and Preservation
Richard Silverblatt Associates, Inc.
Change Order Requisition to HUD
The Guide recommends that the owner does not combine a request for HUD payment of a change order
with other items on the same requisition to HUD, Form HUD-92403-CA. It is possible that there could be
a delay before the HUD inspector determines that the change order work has been completed at the
site and this could hold up payment of the entire owner's requisition. So it is better to put the change
orders on a separate requisition form.